Short answer

The short version of how to follow up with a supplier on a late delivery: confirm the promised date on the purchase order, email the same day for the cause and a new ship date in writing, warn the person waiting for the goods, then phone and escalate one level at a time until a date holds.

Free resource

Download the open order exceptions tracker. The file is a blank CSV with one row per stuck order and columns for the PO, supplier, item, promised date, new date, who owes the next move and days waiting. One example row shows how to fill it in. No account is required.

How to follow up with a supplier on a late delivery: what are the steps?

Following up on a late delivery takes seven steps, two of them waits. Take an order: Noor, a buyer, has a conveyor motor on order with Halden Drives for Rafe Dunmore in maintenance, and the promised date has passed.

  1. Check the PO and the promised date. Noor confirms the date on Halden's order acknowledgment, and that receiving has nothing on the dock.
  2. Email for the cause and a new date. The same day, in the acknowledgment's thread.
  3. Wait for a new date in writing. Noor logs the day she asked.
  4. Warn the requester the same day. Rafe hears it from purchasing, not from an empty dock.
  5. Wait for the real need-by date. The line is running on a spare, and Rafe owes the day the delay starts to hurt.
  6. Phone, then escalate one level. With no reply by the next working day, Noor calls, then asks the account manager.
  7. Record the new date in the ERP. Planning sees the date Halden confirmed in writing. If it is missed, Noor returns to step 2, one level higher.
Following up on a late delivery. 1. Buyer: Checks the PO and the promised date. 2. Buyer: Emails for the cause and a new date. 3. Supplier: Owes a new date in writing (the work waits here). 4. Buyer: Warns the requester the same day. 5. Requester: Owes the real need-by date (the work waits here). 6. Buyer: Phones, then escalates one level. 7. Buyer: Records the new date in the ERP. If "New date missed", go back to step 2.
Workflow diagram: Following up on a late delivery. The amber step is where the work waits on someone else. Select the diagram to enlarge it.

Check the agreed delivery terms and any supplier acknowledgment before calling a date missed. If the confirmation is missing or unclear, ask the supplier to confirm its commitment in writing; the absence of an acknowledgment alone does not decide what the contract requires. Check your own side too, for an invoice that put the account on hold, an unreturned drawing approval or a change made after ordering. Step 5 goes faster when the procurement intake form asked what a late delivery would stop.

What should a late delivery email to a supplier say?

A late delivery email should name the PO and the promised date, and ask for three answers: the cause, a firm ship date, and what can ship now. Leave blame out.

Subject: PO [number], [item]: promised [date], new ship date needed

Hi [Name],

PO [number] for [quantity] of [item] was promised for [date] on your acknowledgment, and we have not received it.

Please reply today with: (1) what caused the delay, (2) the date it will ship, (3) any quantity you can ship now.

If anything on our side is holding the order, tell me and I will clear it today.

Thanks,
[Your name]

Ask for a ship date. "Next week" can mean leaving the supplier's dock or arriving at yours.

The second message says what happens next.

Subject: Re: PO [number], [item]: second request

Hi [Name],

I still need a ship date for PO [number]. I will call you at [time] today. If we cannot speak, I will ask [account manager] for the date.

Thanks,
[Your name]

Who do you escalate to, and in what order?

Escalate one level at a time, and tell your contact before you go above them. Give each level the same facts: the PO, the promised date, when you asked, and what the delay stops.

Level Who What you ask for
1 Your daily contact in inside sales The cause and a ship date in writing
2 The account manager A committed date and a partial shipment
3 Their sales or operations manager A recovery plan with dates
4 Your manager, to their manager Expedite, split the order or release you to buy elsewhere

Formal steps come last. For sales of goods in the United States, the Uniform Commercial Code's section on adequate assurance of performance, 2-609(3), as published by Cornell's Legal Information Institute, reads: "Acceptance of any improper delivery or payment does not prejudice the aggrieved party's right to demand adequate assurance of future performance." That is the text of the provision, not legal advice. Check your state's version and your purchase order terms, and ask your counsel before you send a formal demand or cancel an order.

How does a weekly open order review catch late orders sooner?

A weekly open order review catches late orders sooner by sorting the whole report into the few orders that need a person. The Government of the Northwest Territories' procurement guidelines say: "Expediting should be necessary on only a small percentage of Purchase Orders issued."

Once a week, pull the open order report from your ERP or purchasing system and mark three kinds of order.

Exception The test This week's move
Unacknowledged No confirmed date from the supplier Ask for the acknowledgment
Past due The promised date has passed, nothing received Start the seven steps
Critical A late arrival would stop a line or a customer order Confirm the date before it arrives

For critical orders, ask before the date, on a rhythm that tightens as the need-by date approaches.

How does Noddis keep stuck orders from being forgotten?

Noddis is a project management app that keeps tasks, follow-ups, and related project details connected. When we built Upcoming in Noddis, we put the deadlines from every project in one list, so nothing has to be opened to see what is due.

Noddis holds only the exceptions and who owes the next move. Import the tracker above as a spreadsheet (Free and Pro): each row becomes a task you review before anything is created. Give each task the date you expect an answer, and Upcoming (Free) lists it beside your other deadlines.

Noddis Upcoming for a purchasing team: the deadlines from every sourcing project in one list.
Noddis Upcoming for a purchasing team: the deadlines from every sourcing project in one list. Select the image to view it full size.

Follow-Up shows both waits with their age in days: the supplier's new date under Waiting on Others, your update to the requester under Needs From You. It covers one project on Free and every project on Pro. On Pro you can email the follow-up from Noddis, and the supplier's reply comes back into the thread without the supplier needing an account. A recurring project (Pro) restarts the weekly review on a schedule.

Noddis Follow-Up for a purchasing team: quotes, an order acknowledgment, a ship date and vendor paperwork awaited, plus items owed, each with its age in days.
Noddis Follow-Up for a purchasing team: quotes, an order acknowledgment, a ship date and vendor paperwork awaited, plus items owed, each with its age in days. Select the image to view it full size.

Orders, receipts and payments stay in your ERP. As of November 2026, Noddis does not connect to Outlook, Teams or SharePoint. The procurement follow-up workflow shows the screens, and how procurement managers use Noddis is the longer walk-through.

Your next step

Find the oldest past-due line on your open order report, check the date the supplier acknowledged, and send the first email above today. To record who owes the next move on your own open orders, open the live demo. No account is needed.

Common questions

Should you cancel a late order and buy from another supplier?

Cancel only after you have compared real dates and read your terms. A new supplier's lead time is often longer than the late supplier's recovery date, and custom work in production may carry charges. Get the other quote in writing first, and ask counsel if the terms are unclear.

How do you stop a supplier's dates from moving again?

Ask what the new date depends on: material on hand, a production slot, or a part from their own supplier. A date with a reason can be tested. Ask for the tracking number on the ship date, and log every moved date.

Should the requester contact the supplier directly?

Keep one voice on dates. An engineer or a maintenance lead can join a call to answer a technical question, which often clears the delay. Dates, quantities and any change to the order go through the buyer, in writing, so both companies' records agree.